Dear Ian and all, sorry for the delay. it is now confirmed that there is no change to forms so please kindly proceed for Cambodia. Thanks
Hi @pkhauv , thats good news. Please can you provide us with a list of the forms for us to enable the scoring on?
Thanks!
Hi Ian,
Please find the requirement in the link
Thank very much.
Phanneth
Thanks @pkhauv for sharing this. We’ve done a revision of the feature and it’s looking good! We will do some further QA but this work should be committed and available before the end of the month. Congrats on being the first Data Challenge winners AND the first to get their feature delivered.
Hi everyone,
We have a unique situation that I want to share. In this proposal, we started with a large scope of work. We decided to break it up into chunks bc we considered it too big the DAO. The DAO approved Ian and Awen’s proposal to tackle the first chunk ([Phanneth’s original proposal + Megan’s GBVIMS+ proposal ](Scoring calculation)) , which is now completed and ready to merge and make the payment ($5k). HOORAY!
The second chunk of the work, which was NOT initially approved through the DAO, was making calculations more generally available throughout the system. When the dev team started working on the first part, they realized that it would be impractical and cause future work.
SO, we approved the work for Ian/Awen to finish the job and we will pay they previously quoted amount from the thread above. ($5k)
Potential future work could be exposing this within the UI to allow admins/end users to implement this themselves. This work was initially estimated at $8k. ($5 + $5 + $8k was the initial estimate).
That’s the whole story, feel free to respond here with questions.